Includes Major Capital Improvement projects currently Under Construction as well as projects that are still in the Design/Planning and Study phases. You can also view projects by campus zone.

Master Project List | Completed | Current | Under Construction | Pre-Construction | Impacts

Current Projects
Project Name  Phase  (Est) Start  (Est) End  (Est) Cost 
Bradley ORL Office RenovationPlan/Design Jul 2009 Dec 2009 $3,132,000  
CHS Parking E Clinical Research/Biomarker Seismic RenovationPlan/Design Nov 2009 Dec 2010 $12,800,000  
CNSI-BSL3 LaboratoryConstruction Jun 2008 Aug 2009 $9,160,000  
Hershey Hall Seismic RenovationPlan/Design Jan 2010 Mar 2011 $24,100,000  
Hilgard Graduate Student HousingConstruction Apr 2009 Aug 2010 $24,558,000  
Life Sciences Replacement BuildingConstruction Jun 2007 Aug 2010 $155,378,000  
Medical Plaza 200 - Phase 1 RenovationsConstruction Jul 2005 Jul 2009 $14,187,000  
Pauley Pavilion Renovation & ExpansionPlan/Design Mar 2010 Oct 2012 $185,000,000  
Police Station Replacement BuildingConstruction Jul 2008 Dec 2009 $20,160,000  
Rieber Repairs & RefurbishmentConstruction Jul 2008 Mar 2010 $4,224,000  
Santa Monica/Orthopaedic Replacement HospitalConstruction Apr 2001 Feb 2010 $377,900,000  
Spieker Aquatic CenterConstruction Jun 2008 Aug 2009 $13,900,000  
Telemedicine and PRIME Facilities Phase 1Construction unavailable unavailable $19,700,000  
YRL A Level RenovationConstruction Jan 2009 Aug 2009 $4,368,000  
YRL First Floor Renovation Plan/Design Aug 2009 Jan 2010 $12,950,000 
Total Estimated Cost of Current Projects: $881,517,000